城建 求助】置信仁湖三期交房来源:问政四川 网友:问政网友  2021-09-01 08:44 已回复

Mr.Mayor,

 

Thanks for making some time to read this letter from a foreigner ,I am not a native here,but I chose Suining as my first home in China.My fiancee and I bought an apartment one year ago in ZHIXIN RENHU PARK Phase III ,Pengxi County.

There are some news that was shocking me and unbelievable.its gone be kill me.Why my desired home put on hold for one year?? Why we just get a vaguely answer from developer and local government ??I looked at so many answers and pictures on this platform and its soooo bad for us. They called it LANWEI LOU instead of HOME.How desperate it is for buyers!

I sincerely hope to get a reply from the relevant departments,and thank you for your attention!


官方回复

回复单位:蓬溪县热线办来源:问政四川 回复时间:2021-09-10 16:47

Net friend:
Hello! We have received your inquiry and hereby reply as follows:
1.Investigation:
due to the impact of the COVID-19, ZHIXIN RENHU PARK Phase III was suspended for about three months during the epidemic in 2020. The delivery of buildings 3 to 7 will be delayed on September 30, 2021, and the delivery of buildings 1, 2 and 8 will be on May 30, 2022. Due to the lack of construction force on the construction site, the development enterprise allocated construction force to temporarily suspend buildings 1, 2 and 8 and focus on buildings 3 to 7 in order to ensure the timely delivery of buildings 3 to 7.
2. handling:
Up to now, the exterior decoration of 3 to 7 main buildings has been completed, the remaining door and window glass is being installed, the interior decoration is in the final stage, the water and electricity companies has successively entered the site for construction, and the garden project is being improved. The main buildings of buildings 1, 2 and 8 in phase 3 have been capped, and it is expected to organize workers to enter the site for construction in mid September.
According to the investigation, the buyer purchased the house of Building 1 in phase 3 of Xinxin Renhu garden. The development enterprise made a written commitment that buildings 1, 2 and 8 will be delivered on May 30, 2022.
Finally, thank you again for your trust and support!
Consultation telephone:0825-5428572


网友:
您好!您咨询的问题已收悉,现回复如下:
一、调查情况:
由于受疫情影响,置信仁湖花园3期项目在2020年疫情期间停工三个月左右,3至7栋楼延期于2021年9月30日交房,1、2、8栋交房时间为2022年5月30日。因工地施工力量较少,开发企业为保证3至7栋按时交房,调配了施工力量,将1、2、8栋暂时停工,施工重点放在3至7栋。
二、办理情况:
截至目前,3至7栋主楼外装饰已完成,正在安装剩余门窗玻璃,室内装修正在进行扫尾阶段,水电气公司已陆续进场进行施工,园林工程正在完善。3期1、2、8栋主楼主体已封顶,预计9月中旬组织工人进场施工。
经调查,反映人购买的是置信仁湖花园3期1栋的房屋,开发企业作出书面承诺,1、2、8栋将于2022年5月30日交房。
最后,再一次感谢您的信任和支持!
咨询电话:0825-5428572

同领域留言更多>>

同类别留言更多>>

问政四川所有文字、图像、视频,未经授权不得转载

转载事宜请联系四川日报全媒体 联系电话:028-86968654

蜀ICP备12028253号-2川公网安备51010402000072号

互联网新闻信息服务许可证编号:51120170001

中国互联网违法和不良信息举报中心:12377

四川省互联网不良与违法信息举报中心:028-962377